Aterio flags Oracle's 1.3 GW Wisconsin campus at risk of slipping past its 2027 target on a restarted transmission review

INFRA
Original reporting

Base case in the researcher's analysis puts partial power in December 2027 and full supply in October 2028. A regulator's completeness decision is expected around October 19th.